Taxed their power. Kept signing them up.
The new Democratic governor signed a tax on data centers' electricity. Regulators told the power company to charge them for lines built just for them. Requests from new data centers kept growing.
Data centers are giant buildings full of computers. They use a lot of electricity. On 3 November Ohio elected Amy Acton, who wants to pause new ones until they meet her rules. Here is how the fight works, one picture at a time.
Election results are unofficial until counties finish counting in late November.
Lawmakers write the laws. The governor can say no with a veto. Lawmakers can still win if 3 out of every 5 of them vote to overrule her. Watch what happens in the Ohio House starting in January.
Red dots: Republican seats. Blue: Democratic seats. Empty circles: the votes still missing.
So from January a veto from Gov. Acton sticks, unless 5 to 7 House Democrats join the Republicans. Until then the old House still has 65 Republicans, enough to overrule a veto on its own.
A new data center has to pass through several gates. Different people guard each gate.
SB Energy wants to build a giant gas power plant at Piketon to power Ohio's biggest planned data center. State law gives the Power Siting Board 150 days from a complete application to decide. If it doesn't decide, the plant is approved automatically.
15 Oct application complete · 10 Dec public hearing in Piketon · 6 Jan evidence hearing · 11 Jan Acton sworn in · ~14 Mar decide, or it is approved
That deadline falls about two months after Acton names most of the board, so her board will decide it. Four smaller gas plants for data centers (about 3,000 megawatts together) are at the decision stage now and may be settled before she arrives.
Power Siting Board case 26-0746-EL-BGN (Portsmouth Gas DevCo): application complete 15 Oct 2026, public hearing 10 Dec in Piketon, evidence hearing 6 Jan 2027. Deadline from Ohio Revised Code 4906.10(D); the exact date depends on the board's records. The plant: up to 9.2 gigawatts, first phase 2,000 megawatts (WOSU, 19 Feb 2026; Inside Climate News, 31 Jul 2026).
Each small building stands for 1,000 megawatts: about what one big power plant makes.
A pause on new projects could reach the planned ones, about 14 power plants' worth. It would not switch off the ones running, and the ones being built outside Piketon are mostly too far along. The biggest is one campus at Piketon on U.S. government land, where state power may be weaker, though its gas plant still needs the state's yes.
Counts from Cracked Buckeye's data-center file (196 projects, to 11 October 2026). Many projects give no size, so the true totals are higher.
Every power company in our region buys a promise of enough power for the hottest day, at an auction. When giant new customers like data centers sign up, that promise costs more, and everyone shares the bill.
The price for holding back power jumped from about $29 (for 2024-25) to $329 (for 2026-27, the price cap), per megawatt per day. PJM's market monitor says data-center demand caused most of the jump; an industry consultant puts it near half. Using the monitor's count, Cracked Buckeye estimates it added about $11 a month* to a typical Ohio home's bill in 2025-26. Every price through May 2029 is already set, and the next auction is scheduled for December 2026, before Acton takes office. So a pause now cannot shrink those prices.
* Cracked Buckeye's estimate, not a regulator's.
New high-voltage lines are paid off over about 40 to 60 years. In AEP Ohio's area, a big data center's power deal makes it pay for at least 85% of what it signs up for, for up to 12 years, with an exit fee of 3 years of minimum bills. After that, the rest of the cost can land on everyone else. And most of the load AEP Ohio had signed by February 2026 was signed before that rule existed.
The biggest data center planned in Ohio sits on the same land as one of the biggest single power customers of its time.
Ohio's past shows the pattern: when one giant customer gets a special deal or shrinks, other customers end up paying, sometimes years later. It happened with the coal plants built for Piketon, and with the aluminum smelter at Hannibal: other AEP Ohio customers paid more than $200 million toward its discounted power, and in October 2013, days after regulators approved a new deal, it shut down anyway. AEP Ohio's new data-center rule is built to stop that. No data center has tested it yet.
The lawmakers elected in 2022 keep working until the new ones take over in early January (they meet 4 January). Until then they still have enough Republicans (65 of 99 House seats, 24 of 33 Senate) to overrule a veto from Gov. DeWine. Acton is sworn in on 11 January.
We found no clear case of Ohio passing a law to take powers away from an incoming governor, the way North Carolina and Wisconsin did. In 2006 the clock decided it: lawmakers ended their session, the bill reached the outgoing governor, and it became law before the new governor could veto it (Ohio Supreme Court, 1 August 2007). This year lawmakers are scheduled to meet on 10 and 18 November and 2 and 16 December, plus 9 and 17 December if needed.
The new Democratic governor signed a tax on data centers' electricity. Regulators told the power company to charge them for lines built just for them. Requests from new data centers kept growing.
A July order paused state permits for new data centers of 50 megawatts or more while the state writes tougher rules.
In August and September, grid approvals and state permits froze while the state checked whether the grid could handle them.
Gov. Mills vetoed it because it had no exception for one mill project already under way.
The grid operator stopped new hookups around Dublin. Since December 2025, new big data centers must bring their own power or batteries, on site or nearby.
A new governor inherited a giant factory deal and rewrote it with the company, cutting the most the state could owe by about $2.8 billion.
Here is where Ohio's laws, its history and the other states point.
A special power rate for data centers, limits on tax breaks and water rules. Republican lawmakers already wrote much of this in HB 646.
Local votes are the strongest brake on new data centers right now, and more are coming.
Like New York and Texas. Expect court fights if it tries to stop private building.
Statehouse leaders have not backed one, and the ballot drive for a ban fell far short of the signatures it needed this year. It now aims for 2027.